New Human II: De-installation Schedule
DAY ONE
8:00a—Tajima Studio arrives on-site
Remember to:
**secure the little black springy pieces w hot glue**
**mark shell placement for orientation on interior**
**add USB hub casing**
**use wood or plastic tools to avoid scratching / damaging the surface**
Materials required for de-installation:
2 folding tables
2 saw horses (for NH2 water test)
2 low stepping stools or platforms / apple boxes (Sense Object de-install)
Bucket (NH2 water tests)
Cloths (removal of sealant on bracket / NH2 water test / cleanup)
4 industrial glass suction cups (Sense Object vitrine de-install)
1 dolly
Microfoam sheeting
Cut-resistant gloves (Sense Object de-install)
2 levels
Headlamp
Squeegee
Acetone
2 plastic cups
Paper towels
Washi tape
Goo gone (for ferrofluid cleanup on top of elastomer)
Plastic wrap
Gloves
Empty Ferrotec bottles
Drain pump
Table
Strong tape
Funnel
Hot Glue
8:00a - 5:00p—simultaneous to all work, studio takes measurements of electronics / organizes boxes / materials / takes notes and photos / etc
Estimated time: 1 hour
Handlers required: 1
8:30a—set up tables and materials
shell on floor
Estimated time: 15 minutes
Handlers required: 6
8:45a—remove current fluoroelastomer and sealant from bracket, upper shell perimeter
**use wood or plastic tools to avoid scratching / damaging the surface**
shell on floor
Estimated time: 1 hours
Handlers required: 2
Check for any tears and document
**note the way the existing sealant appears on top for handlers who will apply new sealant**
**fluoroelastomer used during exhibition to be shipped back to Tajima Studio for assessment**
9:45—remove current sealant from lower shell perimeter along weld line
shell on sawhorses
Estimated time: 1 hour
Handlers required: 2
**note the way the existing sealant appears on top for handlers who will apply new sealant**
10:00-10:15a—break
10:15—(cont) remove current sealant from lower shell perimeter along weld line
shell on sawhorses
Estimated time: 1 hour
Handlers required: 1
**note the way the existing sealant appears on top for handlers who will apply new sealant**
11:00a—add white sealant to interior weld line
shell on sawhorses
Estimated time: 30 minutes
Handlers required: 1
Tajima Studio to instruct 1 handler to add sealant to interior weld line
**avoid touching for 90 mins after application of sealant**
11:30—install new gasket and fluoroelastomer
*assess/may need to wait for sealant to cure*
shell on sawhorses
Estimated time: 2 hours
Handlers required: 2 (1 person underneath shell to ensure alignment, 1 person outside)
12:00-1:00p—lunch
1:00p—(cont) installing new gasket and fluoroelastomer
Estimated time: 1 hour 30 minutes remaining
Handlers required: 2
2:30p—check shell on top of interior components
Estimated time: 30 mins
Handlers required: 6
Temporarily install shell onto interior so that Tajima Studio can examine elastomer to ensure elastomer is laying flat
Remove shell and place on sawhorses
**lower slowly onto magnets to ensure they are aligning/level**
3:00-3:15p—break
3:15p— apply white 3M 4200 Marine Grade Sealant underneath along elastomer/shell
shell on sawhorses
Estimated time: 30 min
Handlers required: 1
**avoid touching for 90 mins after application of sealant**
3:45p—move shell from sawhorses to floor
Estimated time: 15 mins
Handlers required: 3
4:00p—handlers finish applying black 3M 4200 Marine Grade Sealant on top along fluoroelastomer/shell (two areas, one between gasket and full fluoroelastomer sheet, another between gasket and shoulder of shell)
Estimated time: 1 hour
Handlers required: 2
Tajima Studio instructs handlers on applying 3M 4200 Marine Grade Sealant on top of shell
DAY TWO
8:00a—Tajima Studio arrives on-site
8:00a - 5:00p—simultaneous to all work, studio takes measurements of electronics / organizes boxes / materials / takes notes and photos / etc
Estimated time: 1 hour
Handlers required: 1
8:30a—lift shell onto sawhorses
Estimated time: 15 minutes
Handlers required: 5
8:45a—set up for water test
Estimated time: 1 hour
Handlers required: 1
Set up using foam/cardboard template underneath, add water
allow to sit for a minimum of 2 hours, ideally longer
10:00-10:15a—break
10:15a—wrap interior electronics w 3M
Estimated time: 15 minutes
Handlers required: 1
12:00-1:00p—lunch
1:00p—check water test, empty and clean
Estimated time: 30 minutes
Handlers required: 1
1:30p—install shell onto interior
Estimate time: 30 minutes
Handlers required: 5
2:00p—wrap and crate
Estimate time: 30 minutes
Handlers required: 5
DAY THREE
**not anticipated**
Contingency work day if any additional work is required
Estimated time: 2 hours, 8-10a (Lara leaves for LAX at 10a)
Handlers required: 2